Middle School Construction

MIDDLE SCHOOL CONSTRUCTION TIMELINE

MIDDLE SCHOOL CONSTRUCTION TIMELINE

  1. June 12, 2020 - Concrete forms are delivered to start framing the walls for the multipurpose room and gymnasium.

  2. June 11, 2020 - The existing HVAC system is cleaned to accommodate new equipment for the addition.

  3. June 10, 2020 - Plumbing connections for the gymnasium restrooms are roughed in.

  4. June 9, 2020 - Water lines have been completed, flushed, and tested.

  5. June 8, 2020 - Grading is completed for new sidewalks leading to the athletic plaza, as well as the bus lane.

  6. June 6, 2020 - Curbing has been installed for the new parking lot.

  7. June 5, 2020 - Concrete pads are poured for the multi-purpose room and the gymnasium.

  8. June 4, 2020 - Final grading and ground stabilization have been completed on the new parking lot next to the track.

  9. June 3, 2020 - A firewall located between the gymnasium and the existing building is completed.